Completed First Project Phase of Gas Interconnection Bulgaria-Serbia

28.12.2015

The total project cost for the Bulgarian part of the connection is 92.6 million BGN, of which Phase 1 "Design", completed by 31st December 2015, amounted to 3.5 million BGN.

Within the implementation of the first phase of the project, a detailed master plan has been developed and approved by the National Expert Council on Spatial Planning and Regional Policy at the Ministry of Regional Development and Public Works. Additionally, the technical project has been developed and approved. Other activities part of the first phase include assessment of the property rights, studies of the archaeological sites along the route, and others.

Source: Ministry of Energy